Response Status
Completed
Response Date
07-Jun-2022 at 01:57:30 PM
As per the RFP, Section 2.4.6.1 – Drainage Design and Construction, the Design-Builder shall review the culverts identified below to determine the replacement requirements and shall consider all possible options/costs for the replacement (detour, roadway protection, trenchless technologies, etc.) and determine the most appropriate option as part of the Drainage Report. Therefore, the foundation scope for non-structural culverts is dependent on the Design-Builder’s design.