View Enquiry: BE 2021-5168-066


Contract Details
Contract Number
2021-5168
Region
Northeastern
Tender Owner
MTO Capital
Location
Highway 631, from Becker Road in Hornepayne, northerly to Negagamisis Narrows Bridge, 31.7 km
Highway
631
Length
31.7
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Design Build Minor - Grading, Drainage, Hot Mix Paving and Structures
Tender Instructions
EXPRESSION OF INTEREST - must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. Local time on March 9, 2022
Contract Dates
Tender Advertise
26-Jan-2022
Tender Opening
06-Jul-2022 at 01:30:00 PM
TRF Submission Opening
08-Jun-2022
TRF Submission Closing
01-Jul-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
02-Jun-2022 at 09:49:35 PM
Type
Other
Subject
Culvert Clean Out
Enquiry
Section 2.4.6.1 (page 71 and page 75; later replaced via Addendum No. 1) – The DB RFP requires “Culverts not being replaced during this Contract shall be cleaned out.” In many instances, these existing culverts have accumulated natural sediment and / or established a stable watercourse, and the requirement to perform cleanout activities may introduce undesirable hydraulic and / or environmental implications. Would the Ministry consider eliminating this requirement in favour of enabling the Design Builder to determine which culverts warrant cleanout based upon existing characteristics?

Response Details
Response Status
Completed
Response Date
07-Jun-2022 at 11:53:17 AM
Response
As per Section 2.4.6.1, Drainage Design and Construction, the RFP states: The Design-Builder shall ensure that adverse drainage impacts to the highway right-of-way and upstream or downstream riparian landowners will not occur. The Design-Builder shall ensure the Work will have no negative impacts to upstream and downstream properties and users.” Therefore, if the DB Contractor feels any work will introduce undesirable hydraulic and / or environmental implications, the work shall be performed (or not performed) in accordance with the requirements of the RFP.