View Enquiry: BE 2022-5008-017


Contract Details
Contract Number
2022-5008
Region
Northeastern
Tender Owner
MTO Capital
Location
From Trout Lake Road Northerly to Estaire Road Interchange
Highway
7279
Length
17.69
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Drainage, Electrical
Tender Instructions
Contract Dates
Tender Advertise
27-Apr-2022
Tender Opening
07-Jul-2022 at 03:00:00 PM
TRF Submission Opening
09-Jun-2022
TRF Submission Closing
01-Jul-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
31-May-2022 at 09:50:15 AM
Type
Items List
Subject
Items 20 & 36
Enquiry
Once the required tonnage of RAP for stockpile and re-use is generated under item 20. Would the contractor have the option to remove all the existing asphalt full depth in one operation ? What is the reasoning for reclaiming 67,000t, when only approx. 25% of that is required on the project ?

Response Details
Response Status
Completed
Response Date
09-Jun-2022 at 01:07:23 PM
Response
Once the required tonnage RAP is generated, the remaining asphalt can be removed by full depth in one operation. 67,000 t RAP is expected to provide 5000t - for Dokis FN, used in the project for RAP shouldering and replacing 30% of the Granular A requirement.