View Enquiry: BE 2022-6019-002


Contract Details
Contract Number
2022-6019
Region
Northwestern
Tender Owner
MTO Regional
Location
Lower Falls Bridge (Site No. 41S-0020/B0) - Highway 609, 3.1 km West of Highway 105.
Highway
609
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Granular Base, Hot Mix Paving, and Structure Replacement.
Tender Instructions
Contract Dates
Tender Advertise
20-Apr-2022
Tender Opening
25-May-2022 at 11:30:00 AM
TRF Submission Opening
20-Apr-2022
TRF Submission Closing
20-May-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
20-May-2022 at 11:46:26 AM
Type
General Conditions
Subject
Modular Bridge Design
Enquiry
Can panel bridge manufacturer design and supply a reinforced bridge that is CHBDC-compliant without the requirement for 10ft reinforcements, as stipulated? Using all 10ft reinforcing chords has no structural advantage and creates extra work for installation. This appears to be an old Bailey Bridge spec, as modern panel bridges with 20ft reinforcement are routinely supplied to MTO for projects across Ontario, and save the installation Contractor and MTO in labour costs. Please confirm that the modular bridge does NOT require all reinforcement to be 10ft.

Response Details
Response Status
Completed
Response Date
25-May-2022 at 07:22:15 AM
Response
Bid according to the contract documents, change proposals submitted by the successful Contractor will be reviewed in accordance with the General Conditions of the contract after award.