View Enquiry: BE 2022-3009-010


Contract Details
Contract Number
2022-3009
Region
West
Tender Owner
MTO Capital
Location
N\A
Highway
401
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MINOR - Grading, Drainage, Hot Mix Paving, Structure and Electrical.
Tender Instructions
EXPRESSION OF INTEREST Must be received electronically as prescribed in the Expression of Interest document by 3:00:00 P.M. local time on; March 30, 2022
Contract Dates
Tender Advertise
23-Feb-2022
Tender Opening
03-Aug-2022 at 01:30:00 PM
TRF Submission Opening
06-Jul-2022
TRF Submission Closing
29-Jul-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
29-Apr-2022 at 03:28:02 PM
Type
General Conditions
Subject
Construction Start
Enquiry
We have reviewed the Ministry’s response to BE 2021-4075-017 and note flooding / wet concerns surrounding the site. We have reviewed the Ministry’s response to BE 2021-4075-025 and echo the concerns raised with starting construction in the winter. Given the wet nature of the site, the major earthworks should be scheduled to occur in the dry. We also note that the schedule provided with the RFP shows the site works, including the SWM Pond, starting and finishing before the design phase (including Environmental Clearance) is completed. Q.1: Could the Ministry please confirm the intent is to start earthworks and SWM pond construction to commence ahead of Environmental Clearance? If so, could the Ministry please update the language surrounding Environmental Clearance in the RFP to include this concept explicitly? The context behind this request is that Environmental Clearance ties to the permits (in this case, the ECA permits for the Oil Grit Separators and the SWM Pond). It is feasible to keep the site’s ultimate drainage system un-operational before permit receipt, but being able to start the construction of earth works and SWM pond while the permit is being obtained. If not: Q.2 We would also request / will the Ministry provide an extension to the contract completion date as noted in BE 2021-4075-025.

Response Details
Response Status
Completed
Response Date
02-May-2022 at 01:52:48 PM
Response
These appear to be intended for 2021-4075, not 2022-3009.