View Enquiry: BE 2021-2124-069


Contract Details
Contract Number
2021-2124
Region
Central
Tender Owner
MTO Capital
Location
FROM 200M SOUTH OF BRADFORD WEST GWILLIMBURY 9th LINE INTERSECTION TO NORTH OF BRADFORD WEST GWILLIMBURY 8th LINE INTERSECTION
Highway
7317
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MINOR: Bradford Bypass – Simcoe County Road 4 (Yonge Street) Underpass.
Tender Instructions
EXPRESSION of INTEREST must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. local time on: November 9, 2021.
Contract Dates
Tender Advertise
08-Oct-2021
Tender Opening
09-Feb-2022 at 01:30:00 PM
TRF Submission Opening
12-Jan-2022
TRF Submission Closing
04-Feb-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
18-Jan-2022 at 09:50:56 AM
Type
Other
Subject
Section 2.4.9.1
Enquiry
Section 2.4.9.1 ‘Groundwater Control – Dewatering / Unwatering’ of the RFP says that “A Category 3 PTTW is currently being obtained and will be available for the Design-Builder upon award”. Section 2.4.11.3 “Permits, Approvals and Commitments” of the RFP requests “to identify any and all permits at the cost of the Design-Builder including Permit to Take Water from MOE as required. A Draft Category 3 PTTW has been submitted to MOECC”. Section 5 of the ‘RTP_2021-12-23 CR4 Groundwater Protection and Well Monitoring Report’ says that “Based on the dewatering estimates provided by AECOM, an EASR is recommended to provide dry working conditions within the excavations event as the total dewatering is anticipated to be a maximum for an excavation at 394,896 L/day”. Can MTO please confirm whether a PTTW Category 3 has been obtained by AECOM and the purpose of this PTTW? It is not clear why AECOM mentions an EASR in the report and applied for a PTTW Category 3.

Response Details
Response Status
Completed
Response Date
24-Jan-2022 at 09:36:07 AM
Response
A PTTW Category 3 has not been obtained by MTO/AECOM, an EASR is recommended. See response to Bid#32: An EASR is required for water taking during construction based on the current DBR Reference Concept design. The EASR is being prepared and will be submitted to the MECP. See Addendum #8 for the Draft Hydrogeological Investigation Report. The Design Builder shall be responsible for reviewing the need for a PTTW submission based on their design.