Please wait...
An error occurred while executing an action
(Check error messages on the page)

View Enquiry: BE 2021-2124-056


Contract Details
Contract Number
2021-2124
Region
Central
Tender Owner
MTO Capital
Location
FROM 200M SOUTH OF BRADFORD WEST GWILLIMBURY 9th LINE INTERSECTION TO NORTH OF BRADFORD WEST GWILLIMBURY 8th LINE INTERSECTION
Highway
7317
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MINOR: Bradford Bypass – Simcoe County Road 4 (Yonge Street) Underpass.
Tender Instructions
EXPRESSION of INTEREST must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. local time on: November 9, 2021.
Contract Dates
Tender Advertise
08-Oct-2021
Tender Opening
09-Feb-2022 at 01:30:00 PM
TRF Submission Opening
12-Jan-2022
TRF Submission Closing
04-Feb-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
06-Jan-2022 at 11:27:31 AM
Type
Special Conditions
Subject
Electrical
Enquiry
Section 2.4.4.2 of the RFP (Page 15) refers to Hydro relocation that is to be completed prior to the contract (Section 1.6 of RFP - Page 2). The composite utility plan (08. BBP-CR4-DBR-Final Utility Composite Plan_2021-09-03.pdf) only shows the existing hydro pole locations and does not show the relocated pole locations. The temporary illumination poles for the detour will need to be placed with clearance to the new hydro pole locations and aerial cables. Temporary power supply is also required and the connection point/transformer location need to be coordinated based on the relocated design. Please provide the hydro relocation design drawings for review.

Response Details
Response Status
Completed
Response Date
17-Jan-2022 at 05:41:54 PM
Response
The utility companies (Hydro One, Bell, Rogers) are planning to relocate all their existing plant to the west side of County Road 4 and, where feasible, to the west of the Reference Concept detour roadway. The utility alignments will generally cross the properties acquired, or being acquired, by MTO on the west side of County Road 4 north of the County Road 4 bridge and adjacent to the N-W Ramp. The draft Hydro One interim and ultimate relocation design is provided in Addendum 8. Hydro One’s interim relocation plans include an overhead relocation on the west side of County Road 4 from a point north of the project limits to a point north of County Road 4 bridge, where there will be an interim termination of the Hydro Lines. The existing hydro lines and poles adjacent to the interim relocation, and south of the interim termination are to be removed. For clarity, there will be no Hydro One connection to 8th Line in the interim configuration. The removal of existing hydro poles in the study area will take place after Bell and Rogers relocations onto the new hydro poles and underground on the west side of County Road 4 have been completed. Bell and Rogers are to complete a permanent underground relocation that provides the necessary underground clearances for the future Bradford Bypass mainline and County Road 4 interchange ramps. The ultimate hydro relocation plans and connection to 8th Line intersection will be completed after the Early Works.