Enquiry Date
10-Dec-2021 at 12:12:17 PM
Type
Other
Subject
End Date of Contract
The end date in the contract is shown to be November 1, 2024. However, the staging drawings, as well as the seasonal shutdown requirements in the operational constraints indicate that work is to occur after the winter of 2024 (seasonal shutdown #3), and into 2025.
Can you please clarify this discrepancy? Please let us know if the end date in the contract is incorrect, or if the staging drawings need to be revised.