Please wait...
An error occurred while executing an action
(Check error messages on the page)

View Enquiry: BE 2022-2001-008


Contract Details
Contract Number
2022-2001
Region
Central
Tender Owner
MTO Capital
Location
From Hwy 427 to Islington Avenue, Including Dixon/Martin Grove Interchange
Highway
401
Length
2.576
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Drainage, Granular Base, Hot Mix Paving, Electrical, ATMS and Structural Length: 4.6 Km
Tender Instructions
Contract Dates
Tender Advertise
10-Nov-2021
Tender Opening
20-Jan-2022 at 01:30:00 PM
TRF Submission Opening
23-Dec-2021
TRF Submission Closing
14-Jan-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
03-Dec-2021 at 10:19:57 AM
Type
Contract Drawing
Subject
Expansion Joints Sequence
Enquiry
Tender documents indicates that the installation of the expansion joints on the bridges are to be completed prior to asphalt paving, contract drawings indicates the expansion joints to be installed after paving. Please clarify which sequence the Ministry would like to proceed with.

Response Details
Response Status
Completed
Response Date
22-Dec-2021 at 11:32:40 AM
Response
Refer to Addendum 1. For the mainline bridges at Dixon and Martin Grove, expansion joints will be installed prior to paving and for the ramp bridges the expansion joints will be installed after paving as shown in the contract drawings.