View Enquiry: BE 2021-2124-019


Contract Details
Contract Number
2021-2124
Region
Central
Tender Owner
MTO Capital
Location
FROM 200M SOUTH OF BRADFORD WEST GWILLIMBURY 9th LINE INTERSECTION TO NORTH OF BRADFORD WEST GWILLIMBURY 8th LINE INTERSECTION
Highway
7317
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MINOR: Bradford Bypass – Simcoe County Road 4 (Yonge Street) Underpass.
Tender Instructions
EXPRESSION of INTEREST must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. local time on: November 9, 2021.
Contract Dates
Tender Advertise
08-Oct-2021
Tender Opening
09-Feb-2022 at 01:30:00 PM
TRF Submission Opening
12-Jan-2022
TRF Submission Closing
04-Feb-2022 at 12:00:00 PM

Enquiry Details
Enquiry Date
03-Dec-2021 at 02:00:15 PM
Type
Other
Subject
Granular/Hot-mix pavement limits
Enquiry
Can MTO please confirm (1) limits of granular and (2) limits of hot-mix pavement at two off-ramp terminals and four on-ramp slip/parallel lanes?

Response Details
Response Status
Completed
Response Date
09-Dec-2021 at 09:44:49 AM
Response
1. The Design Builder shall provide Granular and hot-mix pavement for the on-ramp speed change lanes. 2. For the N-W On-Ramp, N-E On-Ramp, S-W On-Ramp, the granular and hot-mix pavement shall extend up to the bullnose of the on-ramp, and include the full ramp lane width perpendicular to the bullnose along the ramp alignment. 3. For the S-E On-Ramp, the granular and hot-mix pavement shall extend up to the bullnose of the on-ramp and include the full ramp lane width perpendicular to the bullnose along the ramp alignment. The County Road 4 grading and granular platform shall be of sufficient width to accommodate the future re-location of the multi-use pathway once the future interchange is constructed (i.e. between 8th Line and the future multi-use pathway jug handle crossing of the S-E Ramp). 4. For the E-N/S Off-Ramp and W-N/S Off-Ramp, granular and hot-mix pavement are not required. Curb shall be installed along County Road 4 for the interim.