View Enquiry: BE 2019-2119-210


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
14-May-2020 at 11:59:29 AM
Type
Other
Subject
Addendum 8
Enquiry
Addendum 8 provides new drawings profiles for the bridge which references preloading with wick drains and cellular concrete. Additionally the DBR Design Criteria Addendum 1 shows cellular concrete identified for embankment and backfill of abutments. Can the ministry please confirm if these two items are a requirement, or if an alternate design that meets the requirements set out in RFP for settlement can be used.

Response Details
Response Status
Completed
Response Date
19-May-2020 at 04:50:22 PM
Response
Sheet 110B is the only drawing revised in RFP Addendum 8. An alternate design may be considered as long as all RFP requirements are met. Cellular concrete and wick drains are required in the DB Ready Concept Design.