View Enquiry: BE 2019-2119-193


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
20-Apr-2020 at 08:55:03 PM
Type
Other
Subject
Existing conventional poles from STA 17+752 to STA 18+800
Enquiry
Can MTO clarify Addendum 3 Item 4 (2.4.4.1.1 MTO Lighting) bullet 7 refers to all conventional poles not impacted by the proposed construction and not indicated for removal/relocation are to be converted from HPS to LED. The preliminary designs have only shown up to STA 18+800. Will this mean all fixtures from STA 18+800 out to 17+752 at the west limit are also included? If so will this include the tourist information centre facility as well? Could MTO please clarify the electrical limits? Past contracts showing details of the electrical supply and circuits in this area have not been provided.

Response Details
Response Status
Completed
Response Date
01-May-2020 at 02:46:28 PM
Response
Only conventional poles energized by the circuits connected to the existing Distribution Assembly located on York Road in the northeast quadrant of QEW/Glendale Avenue interchange (Supply ‘A’ on Contract 2003-2010) shall be retrofitted with LED luminaires. Please see addendum 10 (RFP Addendum 7) for Contract 2003-2010 reference document.