View Enquiry: BE 2019-2119-163


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
09-Apr-2020 at 03:36:27 PM
Type
Other
Subject
Seasonal Shutdown
Enquiry
Special Provision No. 199F45, August 2019 indicates the following shutdown periods; - November 16, 2020 to May 16, 2021 - November 15, 2021 to May 15, 2022 - November 14, 2022 to April 2, 2023 Typically, the winter shutdown season for highway infrastructure projects is from mid-November to early April. Would MTO consider adjusting the shutdown period end for 2021 and 2022 to early April rather than mid-May? To ensure we include appropriate allowances for all construction activities, is there a reason why the seasonal shutdown for the first two winter periods is approximately 6 weeks longer duration than the third winter season?

Response Details
Response Status
Completed
Response Date
01-May-2020 at 02:38:18 PM
Response
Hotel peak season is from June 1 to Labour Day weekend. The mall peak season from May/June to September 15, and not during or after Canadian Black Friday. Please note that the Seasonal shutdown comes before the Black Friday weekend. This is captured in the MTO SSP 199F01 (MTO lane closure spec). Both of these constraints are captured in the RFP. Refer to RFP Section 2.4.5.2 page 103, and RFP Addendum 3, Item 5 on page 9.