View Enquiry: BE 2019-2119-159


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
08-Apr-2020 at 02:36:15 PM
Type
Other
Subject
RFI #0142 response
Enquiry
As noted in RFI #0142 response, the existing Bell cable located within the existing QEW/Glendale Ave Bridge is to be relocated after the completion of the Glendale contract. Can MTO please confirm if this Bell relocation work will be taken care by the Project Co or Bell itself?

Response Details
Response Status
Completed
Response Date
17-Apr-2020 at 01:23:13 PM
Response
The existing conduits are empty. The proposed Bell work will be taken care of by Bell Canada after the completion of this MTO contract in the future and there is no timeline currently available for the Bell works. The Design-Builder shall notify Bell prior to the empty duct removal works. Future Bell works are not part of this contract.