View Enquiry: BE 2019-2119-161


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
08-Apr-2020 at 02:38:17 PM
Type
Other
Subject
Bell cable at Right-Hand lane on Glendale Ave
Enquiry
As noted in Utility Contact & Status, the cable relocation design for Bell at the Right-Hand turning lane on Glendale Ave has already been completed by March 31, 2020. Can MTO please clarify which right-turning lane it is referring to (i.e. Glendale Ave/York Rd, Glendale Ave/Taylor Rd)? Can MTO please provide the relocation design? Also, please advise if the relocation work is already scheduled to be performed, or it is to be coordinated and carried out by the design builder upon project award. If it is part of the design builder’s responsibility, can MTO please confirm if the civil aspect of the work is to be taken care by the Project Co or Bell itself. Can it be assumed that the cabling work will be taken care by Bell?

Response Details
Response Status
Completed
Response Date
01-May-2020 at 02:37:26 PM
Response
The Bell relocation design is for the Right-Hand turning lane on Glendale Ave located south of Taylor Rd, and shall be completed by Bell Canada. Bell Canada received the MTO encroachment permit on March 26, 2020. The relocation work is anticipated to be completed by May 4, 2020. Please see addendum 10 (RFP Addendum 7) for Bell relocation drawings.