View Enquiry: BE 2019-2119-145


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
27-Mar-2020 at 04:43:54 PM
Type
Other
Subject
Utility information note
Enquiry
In reference to the Utility Contact Information and Status Matrix, the Ministry commented that there is no relocation required for Enbridge Gas however a comment was also provided to note that the vertical clearance of 0.43m from bottom of subgrade will be sloped at 2% within the vicinity of the gas main. Can the Ministry clarify what utility information this note is referring to? Could the Ministry please confirm any ongoing Enbridge works? Can the Ministry also provide Enbridge's third party requirements manual as noted in the Utility Contact Information and Status Matrix.

Response Details
Response Status
Completed
Response Date
02-Apr-2020 at 01:42:02 PM
Response
This note refers to the gas main along the north leg of the York Rd and Glendale Ave intersection. Please refer to the typical sections in the Contract Drawings (Document 29B). Please refer to Document #32 for Enbridge's third party requirements manual. There are no ongoing Enbridge works.