View Enquiry: BE 2019-2119-141


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
27-Mar-2020 at 04:40:27 PM
Type
Other
Subject
NRBR Fibre Optic Cables
Enquiry
In reference to the Utility Contact Information and Status Matrix, the Ministry commented that relocations for NRBN Fibre Optic Cables is completed at Glendale Avenue and York Rd intersection. The Composite Utility Plan provided does not show any NRBN cables at this intersection. Can the Ministry confirm that there is no further relocation of any NRBN cables required as shown on the Utility Composite Plan as per the current design. Can the Ministry also provide mark up drawings of the completed NRBN Fibre Optic Cables Relocation to ensure there are no conflicts with the design.

Response Details
Response Status
Completed
Response Date
01-May-2020 at 02:33:51 PM
Response
NRBN was originally located on the existing Niagara-on-the-Lake Hydro utility poles. These poles have been relocated, and NRBN has elected to relocate their cabling underground. Please see addendum 10 (RFP Addendum 7) for relocation drawings.