View Enquiry: BE 2019-2119-138


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
27-Mar-2020 at 03:36:57 PM
Type
Other
Subject
Project Limits
Enquiry
Section 1.4 The Project states the following: This project is to: - Reconstruct the QEW/Glendale Avenue Interchange to a Diverging Diamond Interchange; - Reconstruct the Glendale Avenue/York Road Intersection to a single-lane roundabout with Channelization; - Construct a new Airport Road loop ramp and connection road from Glendale Avenue to York Road/Airport Road Intersection; - Construct a new commuter carpool lot at the northwest quadrant of the Interchange; - Rehabilitate the pavement on the QEW EB and WB lanes between the east end of Garden City Skyway bridge and QEW/Highway 405 split (~3.0km); and - Extend the right-hand turning lane of Glendale Avenue between Taylor Road and Niagara-on-the-Green Boulevard. Section 1.4 The Project shows the figure attached. As noted above, the scope to rehabilitate the pavement on the QEW EB and WB lanes between the east end of Garden City Skyway bridge and QEW/Highway 405 split (~3.0km) is not consistent with the limits of the contract shown in the figure. Could the Sponsor please clarify the limits of construction and define the rehabilitation scope required within the limits?
Attachment(s)

Response Details
Response Status
Completed
Response Date
07-Apr-2020 at 04:19:56 PM
Response
It is typical for the contract limits to be approximately 2km beyond the new construction limits. Please refer to the Contract Drawings (Document #29B) for the scope and limits of rehabilitation on the QEW.