View Enquiry: BE 2019-2119-101


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
06-Mar-2020 at 05:25:32 PM
Type
Other
Subject
Extension
Enquiry
Can MTO please consider an extension of Technical Proposal Submission to May 4 because proponents have to make an extra effort to confirm construction sequencing given that concept proposed for Stage 2 is not feasible for Ramp E-N/S Detour (cannot accommodate speed change lane) and Ramp W-N Detour (grade differential between Ramp W-S and Glendale Ave would result in detour longitudinal grade of approx. 8%)?

Response Details
Response Status
Completed
Response Date
27-Mar-2020 at 10:26:47 AM
Response
Please refer to RFP Addendum 3 for revised deadlines. Please refer to RFP Addendum 4 for revised contract drawings (Document #29B). QEW Stage 2 typical section has been revised to accommodate the speed change lane. There is an approximately 5% longitudinal grade for Ramp W-N Detour.