View Enquiry: BE 2019-2119-091


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
03-Mar-2020 at 05:29:12 PM
Type
Other
Subject
Storm Sewer
Enquiry
As per RFP document, Section 1.17.3.4.3, it is understood that the design should include any modifications to existing elements. Can MTO please confirm if any modifications are required for the drainage system along the highway median storm sewer?

Response Details
Response Status
Completed
Response Date
09-Mar-2020 at 03:32:10 PM
Response
The minimum requirements for all drainage design are shown in the Contract Drawings (Document #29A). The Design-Builder shall be responsible for the detail design and construction of the entire drainage system within the project limits.