View Enquiry: BE 2014-3014-049


Contract Details
Contract Number
2014-3014
Region
West
Tender Owner
MTO Capital
Location
Highway 401 Reconstruction and Widening from 0.3 km East of Waterloo Regional Road 8 to 0.1 km West of Waterloo Regional Road 24
Highway
401
Length
5.5
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Drainage, Hot Mix Paving, Granular Base, Electrical, Structure Rehabilitation (3) and Structure Replacement (5)
Tender Instructions
Contract Dates
Tender Advertise
04-Feb-2015
Tender Opening
16-Apr-2015 at 03:00:00 PM
TRF Submission Opening
19-Mar-2015
TRF Submission Closing
10-Apr-2015 at 12:00:00 PM

Enquiry Details
Enquiry Date
09-Apr-2015 at 01:04:08 PM
Type
General Conditions
Subject
Item 444 Fibre Wrapping System
Enquiry
With respect to Item 444 Carbon Fibre Wrapping System 1. The specification drawing and notes call for continuous wrapping of both CFRP layers in one wet lay-up application. We would be concerned about this approach as it relates to resin sag, overlaps and just the practicality of applying it well with no voids. It will be difficult to achieve on a columns of this diameter. 2. The quality control provisions require pull-off bond test (Clause 8.02) using 50 mm dollies (which is typical). However, the surface is not flat, it is circular. The only bond test that might typically be applicable would be some form of peel test. Flat bond testing would be possible. 3. Clause 8.03: They refer to preparation of test specimens for tensile properties. They do not describe the frequency of tensile specimens and who is responsible for testing them. Are they made daily? Per m2 of wrap?

Response Details
Response Status
Completed
Response Date
14-Apr-2015 at 12:27:54 PM
Response
1. There shall be no deviation from the wet lay-up process as per the Contract Documents. 2. Testing, as described in section 8 of the specification for Item 444, will be Quality Assurance testing performed by the MTO Contract Administrator. 3. Sampling shall be performed as detailed in subsection 8.01 of the specification for Item 444. Quality Assurance Testing will be performed by the MTO Contract Administrator.