View Enquiry: BE 2019-2119-032


Contract Details
Contract Number
2019-2119
Region
Central
Tender Owner
MTO Capital
Location
From 1.8 km West of Glendale Avenue, Easterly to 1.2 km East of Glendale Avenue; Site No. 18X-0161/B0; and Site No. 090200.
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD MAJOR: QEW / Glendale Avenue Interchange Reconstruction
Tender Instructions
EXPRESSION OF INTEREST must be received electronically as prescribed in the Expression of Interest document by 01:30:00 P.M. local time on: October 30, 2019
Contract Dates
Tender Advertise
25-Sep-2019
Tender Opening
28-May-2020 at 01:30:00 PM
TRF Submission Opening
30-Apr-2020
TRF Submission Closing
22-May-2020 at 12:00:00 PM

Enquiry Details
Enquiry Date
10-Feb-2020 at 11:27:20 AM
Type
Other
Subject
Topographic Survey
Enquiry
Section 1.17.3.4.8 Geomatics states: “A complete topographic survey for the project has been completed as part of the preliminary design phase. The survey file will be made available to the Design-Builder at the start up meeting. The Design-Builder should check the coverage of the provided engineering survey data and use it for the design, as required.” Could the Client please provide the complete topographic survey prior to the RFP Closing for the purposes of design development throughout the Bid phase of the project?

Response Details
Response Status
Completed
Response Date
13-Feb-2020 at 09:37:46 AM
Response
Please see Addendum 5 (RFP Addendum 2).