View Enquiry: BE 2014-3014-010


Contract Details
Contract Number
2014-3014
Region
West
Tender Owner
MTO Capital
Location
Highway 401 Reconstruction and Widening from 0.3 km East of Waterloo Regional Road 8 to 0.1 km West of Waterloo Regional Road 24
Highway
401
Length
5.5
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Drainage, Hot Mix Paving, Granular Base, Electrical, Structure Rehabilitation (3) and Structure Replacement (5)
Tender Instructions
Contract Dates
Tender Advertise
04-Feb-2015
Tender Opening
16-Apr-2015 at 03:00:00 PM
TRF Submission Opening
19-Mar-2015
TRF Submission Closing
10-Apr-2015 at 12:00:00 PM

Enquiry Details
Enquiry Date
16-Mar-2015 at 02:17:23 PM
Type
Other
Subject
Flag Person Days
Enquiry
Should contractor use less flag person days than those specified in the contract, will the Ministry credit the contractor for the savings? Alternatively, if operations are completed in a particular work location of stage prior to the expiry of flag person days, can the remaining days be credited against subsequent operations?

Response Details
Response Status
Completed
Response Date
24-Mar-2015 at 11:19:03 AM
Response
The Ministry is directly billed for the actual flag person days used up to the limit specified in the Contract Documents. As such, the Ministry cannot provide a credit to the contractor. Any flag person days remaining from a completed stage may be carried over or credited to subsequent stages or operations on the same rail line. This has been clarified in Addendum 3.