View Enquiry: BE 2014-2002-079


Contract Details
Contract Number
2014-2002
Region
Central
Tender Owner
MTO Capital
Location
N\A
Highway
401
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD - Structural Bridge Replacement
Tender Instructions
EXPRESSION of INTEREST must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. local time on: August 19, 2014.
Contract Dates
Tender Advertise
16-Jul-2014
Tender Opening
11-Dec-2014 at 01:30:00 PM
TRF Submission Opening
13-Nov-2014
TRF Submission Closing
05-Dec-2014 at 12:00:00 PM

Enquiry Details
Enquiry Date
04-Dec-2014 at 09:07:53 PM
Type
Other
Subject
Subject: Response to BE-2014-2002-041 and BE 2014-2002-64: Existing Drainage Reports and Culvert Inspection Reports
Enquiry
With reference to the Ministry’s response to BE-2014-2002-041 and BE-2014-2002-64: The Ministry’s response instructed the bidder to view the requested Drainage Report and Culvert Inspection Reports for the existing infrastructure within the project limits at the Ministry’s Offices. The Design-Builder has made an appointment and reviewed the material provided at the viewing. For the record, there were no Drainage reports, Culvert Inspection Reports nor Construction Drawings provided that allow the Proponent to verify location, condition or adequacy of the existing drainage infrastructure. Section 2.4.6.2 (Page 60) of the RFP states “The Design-Builder shall include the existing underground drainage systems in their design and, if necessary, re-design and construct the drainage systems to accommodate the new infrastructure including the new structures at the CPR crossing, Campbell Avenue, Sixteen Mile Creek and Appleby Line.” Can the Ministry please provide this information to allow the Design-Builder to define of the scope of the work required with respect to the drainage infrastructure.

Response Details
Response Status
Completed
Response Date
09-Dec-2014 at 12:50:33 PM
Response
All available contract drawings were made available for viewing. Drainage reports and culver inspection reports are not available.