View Enquiry: BE 2014-2002-055


Contract Details
Contract Number
2014-2002
Region
Central
Tender Owner
MTO Capital
Location
N\A
Highway
401
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD - Structural Bridge Replacement
Tender Instructions
EXPRESSION of INTEREST must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. local time on: August 19, 2014.
Contract Dates
Tender Advertise
16-Jul-2014
Tender Opening
11-Dec-2014 at 01:30:00 PM
TRF Submission Opening
13-Nov-2014
TRF Submission Closing
05-Dec-2014 at 12:00:00 PM

Enquiry Details
Enquiry Date
21-Nov-2014 at 11:25:36 AM
Type
Other
Subject
Vertical Alignments
Enquiry
Section 2.4.1.2 Vertical Alignment of the RFP states that the “design parameters identified in the Preliminary Design Report… are to be used in finalizing the alignment”. Since no proposed profiles have provided for the vertical alignment raise in the vicinity of CPR crossing and the lowering of the vertical alignment in the vicinity of Appleby Line in the PDR documents provided it is not possible to comply with this requirement. Please provide Appendix A, B, and J as noted in the Preliminary Design Report. Please provide ‘Appendix A: Preliminary Design Plates’ in CAD format, including all reference files with existing property limits and existing/proposed profiles.

Response Details
Response Status
Completed
Response Date
28-Nov-2014 at 02:32:05 PM
Response
The Preliminary Design Plates (Appendix A of the PDR) were included in the RFP – see Documents 6 and 7 in Table C-1 of Appendix C. The LDD data and CADD files for the Preliminary Design Plates were included in the RFP – see Documents 25 and 26 in Table C-2 of Appendix C. The Preliminary Design Criteria (Appendix B of the PDR) was included in the RFP – see Document 4 in Table C-1 of Appendix C. The Preliminary Construction Schedule (Appendix J of the PDR) was provided. See RFP Addendum #2.