View Enquiry: BE 2014-2003-018


Contract Details
Contract Number
2014-2003
Region
Central
Tender Owner
MTO Capital
Location
Highway 9 Replacement of Holland Drainage Canal Bridge - Site #37-030
Highway
9
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
DESIGN BUILD - Highway 9 Repacement of Holland Drainage Canal Bridge - Site#37-030
Tender Instructions
EXPRESSION of INTEREST must be received electronically as prescribed in the Expression of Interest document by 1:30:00 P.M. local time on March 05, 2014.
Contract Dates
Tender Advertise
29-Jan-2014
Tender Opening
28-May-2014 at 01:30:00 PM
TRF Submission Opening
30-Apr-2014
TRF Submission Closing
23-May-2014 at 12:00:00 PM

Enquiry Details
Enquiry Date
21-May-2014 at 09:11:18 AM
Type
Other
Subject
Pile Design
Enquiry
On page 41 of the RFP, section 2.4.9.2, second paragraph talks about using “closed-end pipe piles” for the new bridge. Then in Appendix D of the Structural Design Report, prepared by Stantec, the preliminary general arrangement drawing shows that for the pier, the steel pipes are to be driven “within steel liners fill with concrete”. What is the reason for the steel liners ?

Response Details
Response Status
Completed
Response Date
23-May-2014 at 07:40:48 AM
Response
The liners were proposed as means of isolating the work from creek flow, minimizing channel impacts for environmental purposes, and reducing muck excavation requirements.