Enquiry Date
13-May-2014 at 12:27:43 PM
Type
Other
Subject
Muck Treatment
Referring to the ministry’s response to BE-2014-2003-013, which was issued on May 6, 2014, we have the follow-up questions below:
a) For doing additional soils investigation, section 1.6 of the RFP states that we have to submit an application minimum 10 business days before the intended date of investigation. Assuming that we get an approval shortly after we submit, we will still require 1 to 2 weeks to get the locates done. Therefore, would the Ministry consider extending the closing date by at least four (4) weeks so we can carry out the additional soils investigation?
b) Alternatively, if an extension of time is not an option, to address the conflicting soils information provided, for bidding purpose, would the Ministry provide the quantity of muck excavation or a sketch showing the limits of the muck excavation ?