View Enquiry: BE 2019-6057-002


Contract Details
Contract Number
2019-6057
Region
Northwestern
Tender Owner
MTO Capital
Location
Winnipeg River Bridge West Branch (Site No. 41S-0124/B0), Hwy 17A, 5.5 km west of Hwy 658; Winnipeg River Bridge East Branch (Site No. 41S-0125/B0), Hwy 17A, 2.4 km west of Hwy 658; Ritchie Road Overpass (Site No. 41S-0128/B0), Hwy 17A, 2.4 km east of Hwy 658
Highway
17A
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Granular Base, Hot Mix Paving, Structure Rehabilitation
Tender Instructions
Contract Dates
Tender Advertise
16-Oct-2019
Tender Opening
20-Nov-2019 at 01:30:00 PM
TRF Submission Opening
23-Oct-2019
TRF Submission Closing
15-Nov-2019 at 12:00:00 PM

Enquiry Details
Enquiry Date
28-Oct-2019 at 11:56:16 AM
Type
Items List
Subject
Management and Disposal of Materials Containing Asbestos
Enquiry
Operational Constraint (Structural) for Partial Depth Concrete Removals refers to abandoned electrical conduit within the barrier walls and the spec reads that the contractor shall take all measures to prevent damage to those conduits during partial depth concrete removal. As per contract documents (Special Provision 101F21), Asbestos is only defined to be present in the Bell/electrical conduits contained within the existing barrier walls. If the intend is to leave the embedded ducts in place, what is the intent and extent of Bid Items 27 and 76, "Management and Disposal of Materials Containing Asbestos"?

Response Details
Response Status
Completed
Response Date
07-Nov-2019 at 08:56:39 AM
Response
Items 27 and 76, Management and Disposal of Materials Containing Asbestos, shall be removed from the Contract in the forthcoming Addendum 1. The Bell/electrical conduits are to remain in place and the Contractor shall avoid disturbance to these conduits during construction.