View Enquiry: BE 2012-6023-022


Contract Details
Contract Number
2012-6023
Region
Northwestern
Tender Owner
MTO Capital
Location
Highway 594, from 0.1 km west of Highway 502, easterly for 4.5 km to the Dryden west limit; Highway 601, from the east junction with Highway 17, northerly for 5.0 km
Highway
594
Length
4.1
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Design Build - Grading, Drainage, Granular Base, and Hot Mix Paving
Tender Instructions
Contract Dates
Tender Advertise
27-Feb-2013
Tender Opening
09-May-2013 at 03:00:00 PM
TRF Submission Opening
11-Apr-2013
TRF Submission Closing
03-May-2013 at 12:00:00 PM

Enquiry Details
Enquiry Date
02-May-2013 at 03:38:16 PM
Type
Other
Subject
GPS Calibration
Enquiry
Page 28 of the proposal documents states, “The design builder is responsible for verifying the status and location of existing monuments, primary and vertical control monuments. The design builder is responsible for ensuring sufficient monuments exist to construct the project.” Will MTO provide the GPS Calibration data from the consultant who prepared the existing B and C plans to assist in the verification of the Horizontal and Vertical monumentation?

Response Details
Response Status
Completed
Response Date
03-May-2013 at 11:48:18 AM
Response
The Ministry will not be providing GPS Calibration Data.