View Enquiry: BE 2019-2002-151


Contract Details
Contract Number
2019-2002
Region
Central
Tender Owner
MTO Capital
Location
From 1.0 km south of Highway 407 ETR northerly to Major Mackenzie Drive; Site No. 37W-0276/B1&B2; Site No. 37W-0277/B1&B2; Site No. 37W-0666/B1&B2; and Site No. 37W-0347/B1&B2
Highway
404
Length
2
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Drainage, Granular Base, Hot Mix Paving, Electrical, ATMS and Structural Length: 13.6 Km
Tender Instructions
Contract Dates
Tender Advertise
06-Mar-2019
Tender Opening
28-May-2019 at 03:00:00 PM
TRF Submission Opening
30-Apr-2019
TRF Submission Closing
24-May-2019 at 12:00:00 PM

Enquiry Details
Enquiry Date
23-May-2019 at 04:36:11 PM
Type
Special Conditions
Subject
Buttonville Airport Constraints
Enquiry
Given the Operational Constraints and Runway Closure Requirements identified in Item 610 that limit the working hours, minimize the number of closures, and the inability to modify construction means/methods to not encroach into the AZR, OLS and Exemption OLS surfaces, there is significant concern about completing the volume of work required in stage 1 by the end of year 1 (ie by Year 1 winter shutdown). Will the MTO consider extending the completion of stage 1 work into year 2?

Response Details
Response Status
Completed
Response Date
27-May-2019 at 03:47:36 PM
Response
MTO does not plan to revise the staging to extend completion of stage 1 into year 2. The Contractor shall close the runway, as necessary, and as per the requirements specified in the Contract, to complete the work.