View Enquiry: BE 2019-2003-019


Contract Details
Contract Number
2019-2003
Region
Central
Tender Owner
MTO Capital
Location
FROM 1.4km NORTH OF BOWEN RD. INTERCHANGE SOUTHERLY TO GILMORE RD. INTERCHANGE / SITE No. 34-129/1 & 2, SITE No. 34-454C, AND SITE No. 34-455C
Highway
1
Length
0
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
GRADING, DRAINAGE, GRANULAR BASE, PAVING, ELECTRICAL, STRUCTURAL, AND ATMS LENGTH: 5.6 km
Tender Instructions
Contract Dates
Tender Advertise
10-Apr-2019
Tender Opening
18-Jun-2019 at 03:00:00 PM
TRF Submission Opening
21-May-2019
TRF Submission Closing
14-Jun-2019 at 12:00:00 PM

Enquiry Details
Enquiry Date
09-May-2019 at 04:13:46 PM
Type
Contract Drawing
Subject
Winter Shutdown
Enquiry
As per specifications. Project completion date is November 2021. In staging drawings only 1 winter is shown. Please confirm the year of this winter and also (after or before) which stage winter 2 will come.

Response Details
Response Status
Completed
Response Date
17-May-2019 at 09:06:21 AM
Response
In Year 1 of construction, traffic operations will not be affected as construction works will occur along the roadside. In Year 2, there will be a winter shutdown. In Year 3, the project will be completed.