View Enquiry: BE 2019-2002-095


Contract Details
Contract Number
2019-2002
Region
Central
Tender Owner
MTO Capital
Location
From 1.0 km south of Highway 407 ETR northerly to Major Mackenzie Drive; Site No. 37W-0276/B1&B2; Site No. 37W-0277/B1&B2; Site No. 37W-0666/B1&B2; and Site No. 37W-0347/B1&B2
Highway
404
Length
2
QMS Declaration
Yes
Option A or B bidding
No
Contract Description
Grading, Drainage, Granular Base, Hot Mix Paving, Electrical, ATMS and Structural Length: 13.6 Km
Tender Instructions
Contract Dates
Tender Advertise
06-Mar-2019
Tender Opening
28-May-2019 at 03:00:00 PM
TRF Submission Opening
30-Apr-2019
TRF Submission Closing
24-May-2019 at 12:00:00 PM

Enquiry Details
Enquiry Date
02-May-2019 at 08:09:20 AM
Type
Other
Subject
Stage 1 Completion
Enquiry
As per the Buttonville Airport Aviation Operation Constraint, it appears as though a minimum of 90 days is required to obtain permits required for construction. Given the aggressive schedule and scope of work to be completed in year 1 prior to winter shutdown, there are significant concerns with being able to complete the allotted work at 16th Avenue within the given year 1 construction period. Will the ministry consider revising the staging and extending the completion of stage 1 into year 2?

Response Details
Response Status
Completed
Response Date
14-May-2019 at 09:38:55 AM
Response
MTO does not plan to revise the staging to extend completion of stage 1 into year 2. MTO has submitted the Land Use Submission Form, Aeronautical Assessment for Obstruction Evaluation, and Buttonville Airport Impact Assessment to the appropriate authorities. MTO expects that these requests will be approved prior to construction start or soon thereafter. MTO has provided the scope and proposed schedule of this project to Transport Canada and is working to expedite approval of the Crane Exemption Requests and avoid any impact to the construction schedule.